The NWT Legislative Assembly just announced that a public meeting will be held on Feb. 6 regarding Taltson.
According to the announcement, the Economic Development and Environment Committee will hear the “Taltson Update” in the Det’anchogh Kų́é (Eagle Room) at the Legislative Assembly in the city of Yellowknife.
The meeting will also be streamed online at www.ntassembly.ca on social media and youtube.
Infrastructure Minister Caroline Wawzonek is also scheduled to attend, according to the message.
Doug Prendergast with NTPC also reported earlier last week that that the company expects to provide an update on the schedule for a return to service of the Taltson Hydro station sometime this month.
Prendergast said in order for services to remain reliable and in order to reduce the environmental impacts within the electricity sector, aging infrastructure will need to be “replaced or refurbished.”
This month alone, the Hay River area including Enterprise and Kátł’odeeche First Nation experienced three outages, lasting under one hour but taking place within a period of about one week.
In 2025, Prendergast spoke about the installation of a permanent solution to the technical issues at Taltson.
“When Taltson returned to service in March 2025 following an almost two-year shutdown to overhaul the hydro unit, NTPC announced that an interim solution to technical issues that were identified earlier this year had been put in place, allowing the unit to return to commercial operation,” said NTPC also indicated that installation of a permanent solution would be installed this summer – the work will be completed during this shutdown,” said Prendergast.
The company arranged to have back up power is set up to support the generator on site. While the work is being done, Prendergast said that there will be increased risks of electrical outages.
“Taltson Hydro has historically been a very reliable source of electricity generation, and we expect it to continue to be reliable once the overhaul has been completed. Switching from diesel back to hydro introduces other potential outage causes such as lightning, wildlife strikes, high winds or tree interference on transmission lines,” said Prendergast.
Currently, the generation capacity of Taltson is 22 megawatts, the plant saw an increase of 4 megawatts when the facility was re-opened in April following the overhaul work that took place beginning in 2023 to the spring of 2025.
On July 30, the Taltson hydro facility went temporarily offline for a planned outage to address identified mechanical issues including the completion of an overhaul project that began in 2023. Fort Smith, Fort Resolution, Hay River, Enterprise and K’atl’odeeche First Nation are among communities with customers that were reverted back to diesel fuel.
The switch to diesel fuel was originally supposed to last about three weeks when a surge tank “corrosion issue” was found, but officials reported that major repairs would be needed before the Taltson station could go back online.
In the fall, the company “identified a path forward” to address repairs to the key piece of equipment, which is part of the aging infrastructure over six decades old at the Taltson Hydro site. “The hydro unit cannot be safely returned to service until the surge tank issue is resolved,” said Prendergast.
The cost of the remediation work was estimated at approximately $15 million, including approximately $5.2 million in production fuel to power the South Slave while Taltson remained offline.
Remediation work was originally estimated to end in December followed by approximately one week of commissioning of the Taltson unit.
It was last spring, the company announced the return of hydro electric power to the South Slave region, with the completion of the Taltson overhaul.
Cory Strang, president and CEO of NWT’s Power Corp called the Taltson overhaul project “one of the largest and most complex projects” in the corporation’s history.
“It faced many challenges, but our team of employees and contractors got the job done. Federal funding support was critical to making this project happen,” said Strang.
Prendergast reported that the total cost for the Taltson Overhaul was approximately $119 million. In their application to the public utilities board, NTPC had previously estimated the total cost for the overhaul was approximately $97.8 million. This included $70 million in project costs and about $45 million in fuel and other operational costs
The overhaul included the replacement of key components like the turbine and turbine shaft, rotor and generator. Ancillary plant equipment such as control panels and vibration monitoring equipment was also upgraded.
The project faced many challenges including a seven-week evacuation of the site because of wildfires in 2023. Then issues were identified during the commissioning process in February 2024 and in early 2025.
“Initially we had an alignment issue, which resulted in a delay of a number of months and then we’ve resolved that. And during commissioning this winter, we found some issues with vibrations that were not anticipated so we needed to get to the bottom of that. That’s been resolved on an interim level,” said Prendergast.
The Taltson Hydroelectric Facility was first built to support the Pine Point Mine in 1965, before expanding services to Fort Smith and Fort Resolution. In 1986, the Taltson facility began providing hydro power to other communities in the South Slave Lake region.