The Northwest Territories Power Corporation has announced that the annual summer maintenance shutdown of the Taltson Hydro Plant has been moved forward to begin on August 16 and is scheduled to last until August 27.
The shutdown was originally scheduled to begin on August 31, but due to the mechanical failure of a key piece of equipment on August 11, the start date was changed to allow repairs of that equipment to begin as soon as possible.
NTPC says that during this shutdown they will also be conducting an inspection of the hydro unit’s runner, the piece within the turbine which drives power generation. The current runner was installed as part of the Taltson Overhaul Project.
During the shutdown, teams will be conducting ariel surveys of towers along the transmission line and removing danger trees in difficult to reach areas. The power station will be taken offline during daytime hours from August 27 to 31 to allow this work to be completed.
NTPC thanks their customers in the South Slave for their patience and understanding while this critical maintenance work is undertaken.