NTPC announced today that their Taltson Station will remain offline until “early” December as the surge tank gets much needed repairs, estimated to cost $15 million. The company reported that the impact on electricity rates “has yet to be determined.”
“Cost recovery and the impact on electricity rates has yet to be determined. Remediation of the surge tank is Phase 1 of a capital project and will be reviewed by the NWT Public Utilities Board (PUB). If approved by the PUB, payment of costs associated with the project would be spread out over the life of the asset,” Prendergast told True North FM.
The company said they have now “identified a path forward” to address repairs to the key piece of equipment, which is part of the aging infrastructure that going upwards of seven decades old at the Taltson Hydro site.
“Aging infrastructure such as the surge tank at Taltson poses significant challenges to NTPC as well as other Canadian utilities,” said Cory Strang, who is the president and CEO of NTPC.
What has been identified as a “corrosion issue” in the surge tank cut customers in the South Slave from the Taltson station since early August. In the meantime, customers have remained and will continue to remain on diesel until December, said Prendergast.
“The hydro unit cannot be safely returned to service until the surge tank issue is resolved,” said Doug Prendergast of NTPC, in the announcement today.
Prendergast added that the remediation work will take about nine weeks and will be followed by approximately one week of commissioning of the Taltson unit.
“This will require South Slave hydro communities to remain on diesel until early December,” he said.
Work on the tank was not part of the planned overhaul this summer.
“Although remediation or replacement of the surge tank was not included in the scope of the Taltson Overhaul, it has been recognized as a future need in NTPC’s five-year capital plan. The cost of the remediation work is estimated at approximately $15 million, including approximately $5.2 million in production fuel to power the South Slave while Taltson remains offline,” said Prendergast
“If this remediation work does not proceed, the South Slave hydro communities would have to remain on diesel generation for the next two years while a new tank is engineered, procured and installed. The fuel and operational costs for this option would likely be in the neighbourhood of $80 million. This remediation project is the first step in a broader, long-term project to replace the surge tank,” added Prendergast.
There is also a planned “second phase” of the project, for the complete replacement of the surge tank to take witin the next couple of years.
“Planning for the second phase has begun and the current concept has a new surge tank being installed upstream of the current tank. The new tank can be built offsite in sections and then transported to the hydro site and welded together. The advantage of this approach is that it can be completed in parallel with the already-scheduled new substation project at Taltson and some costs can be shared. More information about Phase 2 will be provided as planning advances,” said Prendergast
NTPC said that the approach the company has selected, with the remediation of the current tank and upstream replacement in a few years, is the lowest cost option.
“It ensures safe operation, returns the south slave to hydro generation earlier, reduces greenhouse gas emissions and reduces hydro downtime when the second phase of the project runs parallel with the scheduled substation replacement.”
The company has applied for a project permit with the public utilities board.