The Taltson hydro unit is back online and supplying power to the South Slave region.
Northwest Territories Power Corporation president and CEO Cory Strang made the announcement Friday.
“With diesel prices climbing, returning to hydro helps keep energy costs lower for communities,” Strang said.
The power station had been offline since July 2025, forcing communities in the area to rely on diesel generators. The outage, caused by corrosion within the surge tanks, was originally expected to last about three weeks.
Strang said repairs were completed in early March and, after system tests earlier this week, the unit has been brought back online.
“Even after years of extended shutdowns, the investments in the hydro unit and its infrastructure will provide South Slave communities with clean hydropower for many years,” he said.
The station’s overhaul is estimated at more than $100 million, including nearly $18 million contributed by the federal government. The total also covers diesel used to supply power while the plant was offline.